Apply production scenario in production order and planning worksheet
When a default Production Scenario is set up for an Item and Location combination, that Production Scenario is applied when creating a production order. The linked bill of material (BOM), routing, and/or Production Unit of Measure of that default Production Scenario are applied in the production order.
For existing production orders, it is possible to change to another production scenario, using the Change Production Scenario function. This function is available on the (Firm) Planned and Released Production Orders pages and on the Planning Worksheet page to change the applied production scenario in a requisition line.
- Select the Search icon , enter Released Production Orders, and then choose the related link.
The Released Production Orders list page opens. - Select the desired No.
The Released Production Order page opens. - On the Lines FastTab, on the action bar, select Functions > Change Production Scenario.
The Change Production Scenario page opens.
The function is available for Planned, Firm Planned and Released Production Orders. The current Production Scenario is shown with the corresponding Routing, BOM, and Production Unit of Measure. - On the New FastTab, in the New Production Scenario Code field, select a desired code from the list.
Only Production Scenarios that have the same location as the location on the Production Order Line are shown. - Select OK.
As a result, the Production BOM No., Routing No., and Production Unit of Measure are updated. These fields now contain the BOM No., Routing No., and Production Unit of Measure of the selected Production Scenario. The same goes for the Production Scenario Code field. The Production Component lines, and the Production Routing lines are refreshed based on the new BOM No., Routing No., and Production Unit of Measure.
The quantity with the new Production Scenario selected is adjusted according to the respective Quantity (base) and the corresponding Quantity per the Base Unit of Measure. These values are represented on the Change Production Scenario page. In case of a change in the Unit of Measure, the system proposes a change in quantity.
The functionality works similarly on the requisition lines in the Planning Worksheet while adding a line manually or using the Calculate Regenerative Plan function.
TheRouting No. field on the Production Order header is updated in alignment with the Routing No. field in the lines of the Production Order when you select the Change Production Scenario action. In case of multiple Production Order lines, the Routing No. field on the header must be updated manually. The routing number on both the header and lines should consistently remain in sync for accurate production order management.