Replan Production Order

Article • 4/29/2023 • 1 min read

When you use the Replan function, the underlying structure is updated for the Production Order Lines and the Prod. Order Components as the due date is changed.

  1. Select the Search icon , enter Planned Production Order, and then choose the related link.
    The Planned Production Order page opens.
  2. Select the Item in the Source No. dropdown menu.
  3. Enter the Quantity.
  4. On the action bar, go to Actions > Functions > Refresh Production Order.
    The Refresh Production Order page opens.
  5. Choose OK.
  6. In the Prod. Order Components page, change the Due Date for an Item.
  7. On the action bar, go to Line > Excise Data.
    The Excise Lines page opens and the Calculation Date is now changed.
  8. Go back to Planned Production Order page.
  9. On the action bar, go to Actions > Functions > Replan.
    The Replan Production Order page opens.
  10. Choose OK.
  11. On the Lines FastTab, go to Line > Components.
    The Prod. Order Components page opens and the Due Date is updated.
  12. On the action bar, go to Line > Excise Data.
    The Excise Lines page opens and the Calculation Date is now updated accordingly


This works in a similar way on all kinds of production orders.